|

Jackson County Dredging Project 70 Percent Complete
From:
Jackson County News Release Ken Flannigan Filed 8/22/08 GCN
Three cubic yards of silt at a time; that’s
how much silt a dredging “clam bucket” scoops up each time it hits the
water’s bottom. It’s also the standard Jackson County is using to measure
the progress of this summer’s massive dredging projects. With more than
22,300 scoops already removed from four bayous, the County’s dredging is
almost 70 percent complete.
“This dredging is restoring the waterways
that Hurricane Katrina made almost unusable,” says, 2008 Board President
John McKay. “These waterways connect people to the activities that make
living on the Coast unique.”
As Katrina’s flood waters receded from
Jackson County, an estimated 100,000 cubic yards of silt was dumped into
six of the County’s most traveled and used bayous - Chicot, Fort Bayou,
Graveline, Moreton, Ocean Springs Harbor, and St. Martin. On average, this
massive siltation lowered water depth two to three feet throughout each
bayou.
“Katrina reversed a decade’s worth of County
maintenance on these six bayous in a matter of hours. The siltation is
affecting recreational watercraft, commercial watercraft and tidal water
flow patterns throughout the bayous,” Project Manager Butch Loper said.
To restore these six bayous and their
navigable waterways, the Jackson County Board of Supervisors began a
massive dredging project in mid-April 2008. The $2.9 million project will
be completed this fall and is being fully reimbursed by FEMA public
assistance funds.
Dredging is now complete in four waterways –
Ocean Springs Harbor, Fort Bayou, St. Martin and Bayou Chico in
Pascagoula. The dredging barge will now move to Moreton Bayou in St.
Martin followed by Graveline Bayou in Gautier.
Along with dredging, the County is also
planning to build jetties at the mouth of Graveline Bayou and Bayou
Chico. The County is in the process of acquiring permits to build these
jetties. Construction is expected to begin in Bayou Chico next week.
 |